Schedule Outage


Maintenance Shutdown Schedule


The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown. Due to this, the Electricity supply may be affected in the following areas on
26/11/2020
S. NoDisttZoneDESCRIPTIONDate Time fromDate Time toArea affectedTotal Duration (in Hrs)
1 BADLI 516 PREVENTIVE MAINTENANCE 26.11.20 10:00 26.11.20 16:00 PART OF SEC 28 6
2 BAWANA 513 PROJECT WORK 26.11.20 08:00 26.11.20 12:00 PART OF MUNDKAYARD,YOGIRAJ PURAM 4
3 BAWANA 513 PROJECT WORK 26.11.20 08:30 26.11.20 14:30 PART OF MUNDKA YARD 6
6 BAWANA 521 PREVENTIVE MAINTENANCE 26.11.20 10:00 26.11.20 16:00 PART OF LAL FLAT 6
7 BAWANA 533 PROJECT WORK 26.11.20 10:30 26.11.20 14:30 PART OF JAUNTI VILLAGE. 4
13 CIVIL LINES 418 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 16:00 PART OF JAL BOARD COLONY WAZIRABAD 6
14 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 12:30 PART OF SFS PH-4 2
15 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 26.11.20 13:30 26.11.20 15:30 PART OF SFS PH-4 2
19 MANGOLPURI 515 PROJECT WORK 26.11.20 10:00 26.11.20 12:00 PART OF B BLK MGP 2
20 MANGOLPURI 515 PROJECT WORK 26.11.20 14:00 26.11.20 16:00 PART OF B BLK MGP 2
21 MANGOLPURI 518 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 13:00 PART OF S. PUR MAZRA PANNI MKT. AND OM DHRAMA KANTA SIDE. PARTIALY 2
22 MANGOLPURI 518 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 15:00 PART OF U& T BLK M. PURI PARTIALY 4
23 MANGOLPURI 519 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 15:00 PART OF BUDH VIHAR PH-2 SHARMA COLONY 4
24 MODEL TOWN 413 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 13:00 PART OF OUT RAM LANE AREA 2
25 MODEL TOWN 413 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 13:00 PART OF OUTRAM LANE AREA 2
26 MOTI NAGAR 1302 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 13:00 PART OF C-BLK NARAINA VIHAR 3
27 MOTI NAGAR 1302 PREVENTIVE MAINTENANCE 26.11.20 13:30 26.11.20 16:00 PART OF CB TOWEER 3
29 MOTI NAGAR 1303 PREVENTIVE MAINTENANCE 26.11.20 11:30 26.11.20 13:30 PART OF A BLOCK SUDERSHAN PARK 2
30 MOTI NAGAR 1303 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 11:30 PART OF A BLOCK SUDERSHAN PARK 1
32 NARELA 511 PREVENTIVE MAINTENANCE 26.11.20 10:00 26.11.20 11:30 PART OF SAMRIDHI COLONY 1
33 NARELA 511 PREVENTIVE MAINTENANCE 26.11.20 11:30 26.11.20 13:00 PART OF KAUSHIK ENCLAVE 2
34 NARELA 514 PROJECT WORK 26.11.20 11:00 26.11.20 15:00 PART OF SANJAY COLONY, RAJEEV COLONY, PANA MAMUR PUR , PANA MAMUR PUR 4
35 NARELA 517 PREVENTIVE MAINTENANCE 26.11.20 10:00 26.11.20 13:00 PART OF SINGHU BORDAR. 3
36 NARELA 517 PREVENTIVE MAINTENANCE 26.11.20 13:00 26.11.20 16:00 IGL PUMP 3
37 NARELA 517 PROJECT WORK 26.11.20 11:30 26.11.20 15:30 PART OF BAKOLI VILLAGE 4
38 NARELA 517 METERING WORK 26.11.20 11:00 26.11.20 15:00 PART OF BAKOLI VILLAGE 4
39 ROHINI 561 PROJECT WORK 26.11.20 11:30 26.11.20 15:30 PART OF PKT-1 SEC-25 4
43 SHALIMARBAGH 414 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 15:00 PART OF UTTARNCHAL ENCLAVE 4
44 SHALIMARBAGH 414 METERING WORK 26.11.20 12:00 26.11.20 14:00 PART OF CHANDAN VIHAR 2
45 SHALIMARBAGH 505 PREVENTIVE MAINTENANCE 26.11.20 11:00 26.11.20 14:00 PART OF EE BLK 3
46 SHALIMARBAGH 505 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 13:30 PART OF I BLK 3
47 SHALIMARBAGH 505 PREVENTIVE MAINTENANCE 26.11.20 10:30 26.11.20 14:30 PART OF E BLK 4