Scheduled Outage


TATA POWER - DDL Distribution System Outage Request From 11-Jul-2025 To 11-Aug-2025
S. No Discom Distt Zone DESCRIPTION Date  Time from Date Time to Area affected Total Duration (in Hrs)
1 TATA POWER - DDL NARELA 511 PREVENTIVE MAINTENANCE 11.07.25 10:00 11.07.25 16:00 PART OF NANGALI POONA 6
2 TATA POWER - DDL NARELA 511 PREVENTIVE MAINTENANCE 11.07.25 09:00 11.07.25 10:00 PART OF NANGALI POONA 1
3 TATA POWER - DDL NARELA 522 METERING WORK 11.07.25 11:00 11.07.25 13:00 PART OF PKT-13, LABOUR HUTMENTS, SEC-A1 TO A4 2
4 TATA POWER - DDL PITAMPURA 510 PREVENTIVE MAINTENANCE 11.07.25 11:00 11.07.25 13:00 PART OF COMMERCIAL COMPLEX 2
5 TATA POWER - DDL SHALIMARBAGH 414 PROJECT WORK 11.07.25 11:00 11.07.25 13:00 PART OF KAMAL VIHAR 2
6 TATA POWER - DDL SHALIMARBAGH 532 PREVENTIVE MAINTENANCE 11.07.25 11:00 11.07.25 15:00 PART OF JAGATPUR VILLAGE 4
7 TATA POWER - DDL BAWANA 521 PROJECT WORK 12.07.25 08:00 12.07.25 14:00 PART OF C,D,E BLK SEC-5 6
8 TATA POWER - DDL BAWANA 521 PROJECT WORK 12.07.25 09:30 12.07.25 15:30 PART OF B BLK SEC-1 & PART OF A BLK SEC-1 6
9 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 10:00 12.07.25 14:00 PART OF C BLK SEC-1 & PART OF B BLK SEC-1 4
10 TATA POWER - DDL NARELA 522 PROJECT WORK 12.07.25 10:00 12.07.25 16:00 PART OF  I-2022 TO I-2098 6
11 TATA POWER - DDL NARELA 522 PREVENTIVE MAINTENANCE 12.07.25 10:00 12.07.25 16:00 PART OF A-305 TO A-331 6
12 TATA POWER - DDL NARELA 522 PREVENTIVE MAINTENANCE 12.07.25 10:00 12.07.25 16:00 PART OF A-96 TO A-139 6
13 TATA POWER - DDL BADLI 516 PROJECT WORK 12.07.25 10:30 12.07.25 14:30 PART OF BIA 4
14 TATA POWER - DDL BADLI 516 PROJECT WORK 12.07.25 10:30 12.07.25 14:30 PART OF BIA 4
15 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 10:30 12.07.25 12:30 PART OF C BLK SEC-3 2
16 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 10:30 12.07.25 14:30 PART OF G BLK SEC-2 4
17 TATA POWER - DDL NARELA 511 PREVENTIVE MAINTENANCE 12.07.25 10:30 12.07.25 12:30 PART OF NANGALI POONA 2
18 TATA POWER - DDL NARELA 522 PREVENTIVE MAINTENANCE 12.07.25 10:30 12.07.25 12:30 PART OF C-462 TO C-483 2
19 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 11:00 12.07.25 15:00 PART OF N-1 BLK SEC-5 7 PART OF I-1 SEC-5 4
20 TATA POWER - DDL MANGOLPURI 519 PROJECT WORK 12.07.25 11:00 12.07.25 14:00 PART OF PKT-1 SEC-20 3
21 TATA POWER - DDL MANGOLPURI 519 PROJECT WORK 12.07.25 11:00 12.07.25 14:00 PART OF PKT-1 SEC-20 3
22 TATA POWER - DDL NARELA 511 PREVENTIVE MAINTENANCE 12.07.25 11:00 12.07.25 12:00 PART OF NANGALI POONA 1
23 TATA POWER - DDL NARELA 522 PREVENTIVE MAINTENANCE 12.07.25 11:00 12.07.25 13:00 PART OF J-2800 TO J-2809 AND J-2870 TO J-3012 2
24 TATA POWER - DDL PITAMPURA 504 PREVENTIVE MAINTENANCE 12.07.25 11:00 12.07.25 14:00 PART OF B BLOCK MIA PH-2 3
25 TATA POWER - DDL ROHINI 571 PREVENTIVE MAINTENANCE 12.07.25 11:00 12.07.25 13:00 PART OF G.D GOENKA S/STN 2
26 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 11:30 12.07.25 15:30 PART OF N BLK SEC-5 4
27 TATA POWER - DDL NARELA 522 METERING WORK 12.07.25 11:30 12.07.25 13:30 PART OF A-1 TO A-34 2
28 TATA POWER - DDL KESAHAVPURAM 425 PROJECT WORK 12.07.25 12:00 12.07.25 13:30 PART OF SHASTRI NAGAR 1
29 TATA POWER - DDL NARELA 522 PREVENTIVE MAINTENANCE 12.07.25 12:00 12.07.25 14:00 PART OF J-3280 TO J-3291 AND J-3227 TO J-3241 2
30 TATA POWER - DDL NARELA 522 METERING WORK 12.07.25 12:00 12.07.25 14:00 PART OF D-1501 TO D-1521 AND D-1645 TO D-1651 2
31 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 13:30 12.07.25 15:30 PART OF I BLK SEC-1 2
32 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 12.07.25 14:00 12.07.25 16:00 PART OF A BLK SEC-1 2
33 TATA POWER - DDL BAWANA 521 PREVENTIVE MAINTENANCE 13.07.25 11:00 13.07.25 15:00 PART OF D BLK SEC-4 4
34 TATA POWER - DDL MOTI NAGAR 1301 PROJECT WORK 14.07.25 10:00 14.07.25 14:00 PART OF 15 & 20 NG ROAD 4
35 TATA POWER - DDL KESAHAVPURAM 501 PREVENTIVE MAINTENANCE 16.07.25 10:30 16.07.25 13:30 PART OF DSIDC 3
36 TATA POWER - DDL KESAHAVPURAM 501 PREVENTIVE MAINTENANCE 19.07.25 07:00 19.07.25 10:00 PART OF INDUSTRIAL AREA RAMPURA 3