TATA POWER - DDL Distribution System Outage Request From 11-Jul-2025 To 11-Aug-2025 |
S. No |
Discom |
Distt |
Zone |
DESCRIPTION |
Date Time from |
Date Time to |
Area affected |
Total Duration (in Hrs) |
1 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
11.07.25 10:00 |
11.07.25 16:00 |
PART OF NANGALI POONA |
6 |
2 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
11.07.25 09:00 |
11.07.25 10:00 |
PART OF NANGALI POONA |
1 |
3 |
TATA POWER - DDL |
NARELA |
522 |
METERING WORK |
11.07.25 11:00 |
11.07.25 13:00 |
PART OF PKT-13, LABOUR HUTMENTS, SEC-A1 TO A4 |
2 |
4 |
TATA POWER - DDL |
PITAMPURA |
510 |
PREVENTIVE MAINTENANCE |
11.07.25 11:00 |
11.07.25 13:00 |
PART OF COMMERCIAL COMPLEX |
2 |
5 |
TATA POWER - DDL |
SHALIMARBAGH |
414 |
PROJECT WORK |
11.07.25 11:00 |
11.07.25 13:00 |
PART OF KAMAL VIHAR |
2 |
6 |
TATA POWER - DDL |
SHALIMARBAGH |
532 |
PREVENTIVE MAINTENANCE |
11.07.25 11:00 |
11.07.25 15:00 |
PART OF JAGATPUR VILLAGE |
4 |
7 |
TATA POWER - DDL |
BAWANA |
521 |
PROJECT WORK |
12.07.25 08:00 |
12.07.25 14:00 |
PART OF C,D,E BLK SEC-5 |
6 |
8 |
TATA POWER - DDL |
BAWANA |
521 |
PROJECT WORK |
12.07.25 09:30 |
12.07.25 15:30 |
PART OF B BLK SEC-1 & PART OF A BLK SEC-1 |
6 |
9 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 10:00 |
12.07.25 14:00 |
PART OF C BLK SEC-1 & PART OF B BLK SEC-1 |
4 |
10 |
TATA POWER - DDL |
NARELA |
522 |
PROJECT WORK |
12.07.25 10:00 |
12.07.25 16:00 |
PART OF I-2022 TO I-2098 |
6 |
11 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
12.07.25 10:00 |
12.07.25 16:00 |
PART OF A-305 TO A-331 |
6 |
12 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
12.07.25 10:00 |
12.07.25 16:00 |
PART OF A-96 TO A-139 |
6 |
13 |
TATA POWER - DDL |
BADLI |
516 |
PROJECT WORK |
12.07.25 10:30 |
12.07.25 14:30 |
PART OF BIA |
4 |
14 |
TATA POWER - DDL |
BADLI |
516 |
PROJECT WORK |
12.07.25 10:30 |
12.07.25 14:30 |
PART OF BIA |
4 |
15 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 10:30 |
12.07.25 12:30 |
PART OF C BLK SEC-3 |
2 |
16 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 10:30 |
12.07.25 14:30 |
PART OF G BLK SEC-2 |
4 |
17 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
12.07.25 10:30 |
12.07.25 12:30 |
PART OF NANGALI POONA |
2 |
18 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
12.07.25 10:30 |
12.07.25 12:30 |
PART OF C-462 TO C-483 |
2 |
19 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 11:00 |
12.07.25 15:00 |
PART OF N-1 BLK SEC-5 7 PART OF I-1 SEC-5 |
4 |
20 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
12.07.25 11:00 |
12.07.25 14:00 |
PART OF PKT-1 SEC-20 |
3 |
21 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
12.07.25 11:00 |
12.07.25 14:00 |
PART OF PKT-1 SEC-20 |
3 |
22 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
12.07.25 11:00 |
12.07.25 12:00 |
PART OF NANGALI POONA |
1 |
23 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
12.07.25 11:00 |
12.07.25 13:00 |
PART OF J-2800 TO J-2809 AND J-2870 TO J-3012 |
2 |
24 |
TATA POWER - DDL |
PITAMPURA |
504 |
PREVENTIVE MAINTENANCE |
12.07.25 11:00 |
12.07.25 14:00 |
PART OF B BLOCK MIA PH-2 |
3 |
25 |
TATA POWER - DDL |
ROHINI |
571 |
PREVENTIVE MAINTENANCE |
12.07.25 11:00 |
12.07.25 13:00 |
PART OF G.D GOENKA S/STN |
2 |
26 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 11:30 |
12.07.25 15:30 |
PART OF N BLK SEC-5 |
4 |
27 |
TATA POWER - DDL |
NARELA |
522 |
METERING WORK |
12.07.25 11:30 |
12.07.25 13:30 |
PART OF A-1 TO A-34 |
2 |
28 |
TATA POWER - DDL |
KESAHAVPURAM |
425 |
PROJECT WORK |
12.07.25 12:00 |
12.07.25 13:30 |
PART OF SHASTRI NAGAR |
1 |
29 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
12.07.25 12:00 |
12.07.25 14:00 |
PART OF J-3280 TO J-3291 AND J-3227 TO J-3241 |
2 |
30 |
TATA POWER - DDL |
NARELA |
522 |
METERING WORK |
12.07.25 12:00 |
12.07.25 14:00 |
PART OF D-1501 TO D-1521 AND D-1645 TO D-1651 |
2 |
31 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 13:30 |
12.07.25 15:30 |
PART OF I BLK SEC-1 |
2 |
32 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
12.07.25 14:00 |
12.07.25 16:00 |
PART OF A BLK SEC-1 |
2 |
33 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
13.07.25 11:00 |
13.07.25 15:00 |
PART OF D BLK SEC-4 |
4 |
34 |
TATA POWER - DDL |
MOTI NAGAR |
1301 |
PROJECT WORK |
14.07.25 10:00 |
14.07.25 14:00 |
PART OF 15 & 20 NG ROAD |
4 |
35 |
TATA POWER - DDL |
KESAHAVPURAM |
501 |
PREVENTIVE MAINTENANCE |
16.07.25 10:30 |
16.07.25 13:30 |
PART OF DSIDC |
3 |
36 |
TATA POWER - DDL |
KESAHAVPURAM |
501 |
PREVENTIVE MAINTENANCE |
19.07.25 07:00 |
19.07.25 10:00 |
PART OF INDUSTRIAL AREA RAMPURA |
3 |